Project Intelligence Framework
by BI DEVELOPMENT

Project Manager manual

All manuals ·
  1. 01What Project Intelligence Framework does
  2. 02Before you start
  3. 03Install and connect
  4. 04Setup: three answers
  5. 05Your working day
  6. 06Your first project
  7. 07Your first project (continued)
  8. 08The Toolkit
  9. 09Reading the morning report
  10. 10Follow-ups as drafts
  11. 11Your PM report
  12. 12Minutes of Meeting
  13. 13The governance document
  14. 14Technical specification from Excel
  15. 15Reference and support
Project Intelligence Framework
by BI DEVELOPMENT
Project management, every morning

Project Intelligence Framework

Project Manager manual
For the Project Manager
From the first ten minutes to the daily routine: install, set up, create a project, read the morning report, send what Claude prepared.
Project Manager manual
Project Intelligence Framework
by BI Development
Project Intelligence Framework · PM manual
Overview

What Project Intelligence Framework does

Project Intelligence Framework is a plugin for Claude. It reads what moved in your projects overnight and has the morning ready before you are: the report, the follow-ups, the minutes.

Your day with it
Before you start
Reminder on your phone
The reports start at your start time
Every morning
One report per project
Status, roadmap, blockers, delays, decisions
Prepared, not sent
Drafts in Outlook
Follow-ups in the right thread, to the right people
You
Read, correct, send
Nothing reaches anyone else without you
What it reads
Source
What it takes
Outlook mail
Every mail that carries the project code: confirmations, dates, open questions
Outlook calendar
Meetings of the coming days, who accepted, who declined
Teams
Meeting transcripts, for the minutes
Project Toolkit
The Excel plan you keep: tasks, owners, dates, milestones, RIDA (risks, issues, decisions, actions), people
What always stays yours
The decision. Claude prepares drafts; only you send them. The one mail it sends by itself goes to you.
The truth. Missing data is never hidden: it stays in the report until someone fills it in.
The data. Mail, calendar and files stay in your Microsoft 365. Your own Claude reads them through your own connection.
Project Intelligence Framework by BI Development
02 / 16
Contents ↑
Project Intelligence Framework · PM manual
Start

Before you start

Seven things, checked once. If one is missing, the setup tells you which one and stops.

What
Why
Where it comes from
A Claude plan
The plugin runs inside Claude. Daily reports on several projects need a plan with enough usage
claude.ai, your own subscription
The Claude desktop app
The morning reports are built and delivered while your computer is on and the app is open
claude.ai/download
OneDrive sync on the computer
Each project folder is synced to your computer, so Claude reads your project files quickly
Microsoft 365, already on your computer
A Microsoft 365 work account
Outlook, calendar, Teams and OneDrive or SharePoint
Your organisation
A PIF licence
Activates the plugin for your work account
BI Development, by e-mail
The plugin file
The plugin you add to Claude
pif.bidevelopment.ro/download
Two connectors in Claude
Microsoft 365 (your mail and files) and BID (your licence)
Next page
The licence belongs to one work account. The address in your licence e-mail is the only address the plugin is allowed to send mail to: your own.
Good to know

Your projects are kept in two places you choose: a working folder for your settings (your office) and one place for the project folders. Both are folders in your OneDrive or in SharePoint, synced to your computer; never a folder that exists only on the computer.

Project Intelligence Framework by BI Development
03 / 16
Contents ↑
Project Intelligence Framework · PM manual
Start

Install and connect

Ten minutes, once. You need the plugin file from pif.bidevelopment.ro/download and the connector address from your licence e-mail.

1
Install the plugin
Download bid-pmo-<version>.zip from pif.bidevelopment.ro/download. In Claude, open the plugins settings and upload it. The plugin appears as bid-pmo.
2
Connect Microsoft 365
In Claude's connectors, connect Microsoft 365 and sign in with your work account. This is how Claude reads your mail, calendar and files.
3
Connect BID
Add a custom connector named bid with the address from the licence e-mail. When asked, choose to register automatically and sign in with the same work account.
4
Check
Start a new chat and type /bid-pmo:pif-setup. If a connector or the licence is missing, Claude says which one in one sentence and stops.
Start a command from the menu
1.Type / in the message box.
2.Pick the command from the menu (e.g. bid-pmo:pif-new-project).
3.Add the details after it, if any (e.g. RO-005 - Project name), then send.
Do not paste a command copied from a text: a trailing dot or space turns it into a plain message.
If it does not work
You see
Most likely
What to do
no_licence
The work account you signed in with is not the licensed one
Sign in to the BID connector with the account from the licence e-mail
licence_inactive
The licence is paused or ended
support@bidevelopment.ro
Microsoft 365 missing
The Microsoft 365 connector is not connected
Step 2
Project Intelligence Framework by BI Development
04 / 16
Contents ↑
Project Intelligence Framework · PM manual
Start

Setup: three answers

/bid-pmo:pif-setup asks only what it cannot find out by itself. Three answers, then the plugin works for you every working day.

Start a command from the menu
1.Type / in the message box.
2.Pick the command from the menu (e.g. bid-pmo:pif-new-project).
3.Add the details after it, if any (e.g. RO-005 - Project name), then send.
Do not paste a command copied from a text: a trailing dot or space turns it into a plain message.
1
Your office
A folder in your OneDrive or in SharePoint where the plugin keeps your settings and project cards. Claude proposes the name BID PMO and shows you the link before saving. OneDrive: only you see it. SharePoint: the site members see it and the data stays with the company.
2
Your signature
Your name and the company you represent, as they will close every draft. Claude proposes the name from your address; you confirm.
3
Your start time
When your day starts: computer on, Claude app open. The reports are scheduled from it.
What you get back
✅ Installed · Licence active · Address: your own (from the licence) · Office: the folder link · Signature as it will appear · First report at your start time + a few minutes · Next step: your first project

Your address is not asked: it comes from the licence. All other settings start with sensible defaults; they are listed in your office, in config/board.md (last page).

Project Intelligence Framework by BI Development
05 / 16
Contents ↑
Project Intelligence Framework · PM manual
Daily

Your working day

Monday to Friday, on your start time. Projects are staggered so that each report is ready one after the other.

Start time − 10 min
Reminder
On your phone: turn on the computer, open Claude
Start time + a few min
Project 1
Report, drafts
Then
Project 2, 3 …
One after the other, by project code
Last
Your PM report
Only for you
Rules
The reminder runs in the cloud and needs nothing on your side. The reports need your computer on and the Claude app open, because they run there. The report PDF is written to SharePoint by the BID server.
Change your start time, add or close a project: the whole schedule is recalculated in the same run and you see the new times.
A project that must run at a fixed hour can keep its own hour; the others are staggered without it.
Missed a morning? Nothing is lost. The next run reads everything since the last report.
Project Intelligence Framework by BI Development
06 / 16
Contents ↑
Project Intelligence Framework · PM manual
Projects

Your first project

/bid-pmo:pif-new-project creates everything a project needs in about two minutes. Each line is marked done only after Claude has checked it.

Run it in any chat — a new one per project is recommended. Your setup is kept on the BID server and in your office, not in the chat. For the folder-sync step at the end, open that chat in the Claude desktop app on your computer.

Start a command from the menu
1.Type / in the message box.
2.Pick the command from the menu (e.g. bid-pmo:pif-new-project).
3.Add the details after it, if any (e.g. RO-005 - Project name), then send.
Do not paste a command copied from a text: a trailing dot or space turns it into a plain message.
1
Code and name
A short code (capital letters, dash, digits, e.g. AB-001) and the project name. The code goes into every mail subject of the project: it is how the plugin recognises the project.
2
Where projects live (first time only)
One folder for all your projects, in SharePoint or your OneDrive. Asked once, then remembered.
3
Governance document (yes / no)
Yes when the business must confirm in writing what the project delivers. The Key User receives a questionnaire (see “The governance document”).
Project Intelligence Framework by BI Development
07 / 16
Contents ↑
Project Intelligence Framework · PM manual
Projects

Your first project (continued)

What is created
Item
Content
Project folder
<CODE> - <name>, with Notes for minutes and PI for the daily reports
Toolkit
<CODE> - Toolkit.xlsx: the project plan you keep (next page)
Governance
Only with governance = yes: the folder Governance/Input with the Key User questionnaire
Evaluation
The folder Evaluation with <CODE> - PM Evaluation Form.pdf: the Key User and the SA rate the project and the PM at Go-Live or closure. You decide when to send it.
Project card
In your office: what the plugin needs to know about the project
Then, on your computer, once per project

Sync the project folder with OneDrive (SharePoint: the library's Sync button) and add the local folder as a connected folder in the Claude desktop app. Claude then records where it is. Without it the morning mail comes without the PDF; run /bid-pmo:pif-new-project again later and it completes only this step.

Last step, yours: fill in the Toolkit, starting with the Project Charter and the Stakeholder Matrix. Until then you are the only member of the project.
Project Intelligence Framework by BI Development
08 / 16
Contents ↑
Project Intelligence Framework · PM manual
Projects

The Toolkit

The Toolkit is the single source of truth of the project. The report reads it at every run; nothing is copied elsewhere.

Sheet
What you keep there
Project Charter
Code, name, scope and out-of-scope, Process Book (the name and date of the document that describes the project's processes), current phase, planned start, estimated end date, and Project Status: Ongoing, On hold, Completed or Cancelled
Phases
Your phases, in order, each with its Phase Start, Phase End and Red Mark buffer (5% to 50%). Buffer Date and Status are calculated. The other sheets choose from this list
Execution Tracker
Tasks: phase, owner, Baseline Due, due date, Delayed to, Dependency, status, comments
RIDA Register
Risks, Issues, Decisions, Actions: owner, criticality, due date, Open / Closed
Stakeholder Matrix
Everyone in the project: role, organisation, e-mail, how often they get the report
Resources availability
Who is away and when: holidays, leave, public holidays
Rules that make the report right
A task whose name contains (MS) is a milestone: it appears on the roadmap as M1, M2 …
A late task gets a Delayed to date and a comment; until you set it, the report shows it late to today. A task with a Dependency starts after its predecessors.
Status: Pending, Planned, In Progress, Blocked, Completed, Cancelled. Pending = not started; Planned = dated and ready.
Who is away goes into Resources availability: those days do not count as late.
Phase Start and Phase End are the plan of reference: they do not move when tasks slip, so the report sees a pushed phase. Missing, they are filled in once from the tasks' original dates, and the report says so.
Set Project Status to On hold, Completed or Cancelled and the project stops: no report, no drafts, one line in your PM report. Claude then removes its scheduled task. To restart, set it back to Ongoing and run /bid-pmo:pif-setup.
Project Intelligence Framework by BI Development
09 / 16
Contents ↑
Project Intelligence Framework · PM manual
Daily

Reading the morning report

One PDF per project, every morning, in the project's PI folder. Your mail brings its header and the link. Read from the top: the first page says whether you need to act.

Part
What it tells you
Status
RED: a phase is pushed past its Buffer Date. YELLOW: a phase pushed past its Phase End but not past its Buffer Date, a task past its due date, or a question unanswered for 24 hours; all of them are listed. GREEN: none of these
Roadmap
The whole project on one picture: phases, milestones M1… with ✓ done, red late (+working days), today's line
Reason · Main concern
The facts behind the status, each with its source and time
Immediate actions · Blockers
Who must do what, by when; what blocks what
Key decisions · Timeline
What was decided, by whom; the next 5–7 days per person
Open action items
Every open item with owner, due date, follow-up state and the mail thread
Risks · RIDA · Meetings
Scored risks, open RIDA lines, the next meetings and who declined
Incomplete data
What is missing in the Toolkit or contradicts the mail. Fill it in and it disappears
All times are in one time zone, the one in your settings. Every fact carries its source: a mail, a Toolkit sheet, a meeting.

Stakeholders get the report as a ready draft, as often as their column in the Stakeholder Matrix says: daily, weekly or monthly.

Project Intelligence Framework by BI Development
10 / 16
Contents ↑
Project Intelligence Framework · PM manual
Daily

Follow-ups as drafts

Follow-ups are written for you, as Outlook drafts, in the thread where the subject was discussed. You read, correct and send.

When a draft appears
Moment
Draft
To
The due day of a task
A short reminder
Only the owner
After the due day, still not done
A follow-up
Everyone in the thread, or the owner with the others in copy
A mail waits for your answer
A reply
Everyone in the original mail
When no draft appears, on purpose
The owner cannot work yet: something they need is missing, or it depends on an event that has not happened.
Someone already gave a date: the plugin waits for it.
Your own message already closed the loop, or your silent-acceptance clause applies.
A draft when you ask for one

For one mail of a project, type /bid-pmo:pif-draft with the project code and what identifies the mail (e.g. RO-005 invoice format).

Where it looks
Seven sources: the thread, the project's other mails, their attachments read in full, the Toolkit (all its sheets), the minutes in Notes, the Teams transcripts of the project meetings and the documents in the project folder
What goes in
Only what the stakeholders said or confirmed. What was only said in a meeting is written as discussed, not as decided. A line in the Toolkit or a document that nobody confirmed is not presented as a decision
What you get
A reply draft in the same thread, never sent, and in the chat the source of each point and what is missing
When the answer needs your decision, Claude asks you first and writes the draft after you answer.
Nothing is ever sent to a stakeholder. A guard inside the plugin blocks every send, except to your own address. Every draft has the project code in the subject and ends with your signature.
Project Intelligence Framework by BI Development
11 / 16
Contents ↑
Project Intelligence Framework · PM manual
Daily

Your PM report

After the last project, one mail only for you: [PM only] PM report. Every working day, even when there is nothing to say: silence would look like a failed run.

One section per project
Part
What
Drafts created
Who, for what, reminder or follow-up, and the draft's subject
Considered and rejected
A follow-up the plugin chose not to write, and why: deadline not reached, depends on another step, already chased, silent acceptance
Omitted from the report
What was kept out of the stakeholders' report, and why: confidential, personal, sensitive
Attention
What needs your eye: a source read only in part, a delivery problem, a draft to check

A project whose report did not run says so in one line. A quiet day says Nothing for the PM today.

This mail goes only to your own address, never to anyone else, and is never forwarded. It is the one mail the plugin sends instead of drafting.
Project Intelligence Framework by BI Development
12 / 16
Contents ↑
Project Intelligence Framework · PM manual
Meetings

Minutes of Meeting

Record the meeting in Teams. Ask Claude for the minutes, or type /bid-pmo:pif-minutes with the meeting title.

Start a command from the menu
1.Type / in the message box.
2.Pick the command from the menu (e.g. bid-pmo:pif-new-project).
3.Add the details after it, if any (e.g. RO-005 - Project name), then send.
Do not paste a command copied from a text: a trailing dot or space turns it into a plain message.
1
Claude reads the transcript
Speakers come from Teams. When it is not sure who said what, it asks you instead of guessing.
2
The minutes are saved
A Word file in the project's Notes folder: <CODE> - <meeting> - MOMddmmyy.docx, with highlights, decisions, action items with owners and dates, a timeline.
3
A draft for you
A new mail, <meeting> - Review ddmmyy, without attachment: the participants in To, the invited people who did not attend in Cc. An address missing from the Stakeholder Matrix is never guessed: it is listed in the summary.
4
You validate
Read the mail, attach the minutes and press Send.
5
The evening loop
Claude compares what you sent with what it wrote and asks why you changed it: next time it writes closer to you.
The next morning's report reads the action items straight from the minutes in Notes. The Execution Tracker stays yours to keep.
Project Intelligence Framework by BI Development
13 / 16
Contents ↑
Project Intelligence Framework · PM manual
Business

The governance document

When the business must confirm what the project delivers, the Key User answers questions about their own work, not project vocabulary.

You
Send the questionnaire
Governance Input.xlsx, from Governance/Input
Key User
Answers
Steps, business cases, attachments
You
Save it back
Same name, same folder
Claude
Builds the document
Scope, rules, scenarios, sign-off
The questionnaire
Sheet
One row is
1 Your process
One step: who does it, how today, in the project or not, limits, who approves, mandatory data, what must never happen, how it is checked
2 Business cases
One situation from start to end, what can go wrong and what should happen then, how you know it worked
3 Attachments
A file the Key User already has, e.g. an Excel with prices or rules
Save the answered file over the empty one, with the same name, in the same folder. Every unanswered question appears in the morning report as an open item of the Key User. None counts as an answer; an empty cell does not.
Project Intelligence Framework by BI Development
14 / 16
Contents ↑
Project Intelligence Framework · PM manual
Business

Technical specification from Excel

A Key User's Excel with calculations (a price calculator, a planning sheet) becomes a technical specification a developer can build from.

1
Put the Excel in Governance/Input
List it in the questionnaire's 3 Attachments as Technical specification.
2
Ask for the specification
Type /bid-pmo:pif-tech-spec with the file name.
3
Review in plain language
Inputs, calculations explained in words, reference tables, outputs, mandatory test cases, every inconsistency found (e.g. a value typed over a formula) and the open questions.
4
The Requester answers the delivery questions
How the output is delivered: format, recipients, channel, timing, what happens when data is missing. Each question shows who answers it: Key User or Requester.
5
Key User corrections, then sign-off
The same people who sign the governance document.
Start a command from the menu
1.Type / in the message box.
2.Pick the command from the menu (e.g. bid-pmo:pif-new-project).
3.Add the details after it, if any (e.g. RO-005 - Project name), then send.
Do not paste a command copied from a text: a trailing dot or space turns it into a plain message.
The developer gets a clean PDF with a dedicated Output chapter; the Key User reviews a version without technical terms. Unanswered questions appear in the morning report as open items of the person asked.
Project Intelligence Framework by BI Development
15 / 16
Contents ↑
Project Intelligence Framework · PM manual
Reference

Reference and support

The commands, your settings and where to get help.

Command
What it does
/bid-pmo:pif-setup
Install, change the office or the start time
/bid-pmo:pif-new-project
Create a project
/bid-pmo:pif-pi-report CODE
Run the morning report of one project now
/bid-pmo:pif-minutes
Minutes of a recorded meeting
/bid-pmo:pif-draft CODE + mail
A reply draft for one mail of a project, from what the stakeholders already said
/bid-pmo:pif-governance
Build the governance document
/bid-pmo:pif-tech-spec
Technical specification from a Key User's Excel
Start a command from the menu
1.Type / in the message box.
2.Pick the command from the menu (e.g. bid-pmo:pif-new-project).
3.Add the details after it, if any (e.g. RO-005 - Project name), then send.
Do not paste a command copied from a text: a trailing dot or space turns it into a plain message.
Your settings

All settings live in your office, in config/board.md: one line each, with its code (P01, P02 …), its value and what it does. Change a value there; the next run uses it. Times, thresholds, report windows, signature: nothing is fixed in the plugin.

Your data

Mail, calendar, Teams and files are read through your own Microsoft 365 connection and stay where they are. The plugin's instructions are licensed to you: they are delivered at every run and are not stored on your computer.

Support

support@bidevelopment.ro · write the project code only if the question is about one project; never send passwords or licence keys.

Project Intelligence Framework by BI Development
16 / 16
Contents ↑